DIT Test Schedule 2Q 2008

April 2008

Date Cycle Date Holdings Database Hours Testing Notes
April 1, 2008 N/A N/A N/A Closed - Refresh Databases
April 2, 2008 4/2/2008 03/31/2008
No P&I activity processed.
7:30 a.m. - 11:30 p.m.  
April 3, 2008 4/3/2008 Prior day test activity applied.P&I payment wires processed through the end of the month. P&I notifications available upon request. 7:30 a.m. - 11:30 p.m. Disruptive testing: 6:00 p.m. - 6:50 p.m.
XRF takeover: 7:15 p.m. - 8:15 p.m.
April 4, 2008 4/4/2008 Prior day test activity applied. 7:30 a.m. - 11:30 p.m.  
April 5, 2008 4/4/2008 continuation of testing from Friday 10:00 a.m. - 2:00 p.m.  
April 6, 2008 N/A N/A N/A Testing not available
April 7, 2008 4/7/2008 Prior day test activity applied. 7:30 a.m. - 11:30 p.m. XRF takeover: 8:30 a.m. - 9:30 a.m.
Disruptive testing: 3:00 p.m. - 3:50 p.m.
April 8, 2008 4/8/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m.  
April 9, 2008 4/9/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m.  
April 10, 2008 4/10/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m. Disruptive testing: 6:00 p.m. - 6:50 p.m.
XRF takeover: 7:15 p.m. - 8:15 p.m.
April 11, 2008 4/11/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m.
April 12, 2008 4/11/2008 continuation of testing from Friday 10:00 a.m. - 4:00 p.m.
April 13, 2008 N/A N/A N/A Testing not available
April 14, 2008 4/14/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m. XRF takeover: 8:30 a.m. - 9:30 a.m.
Disruptive testing: 3:00 p.m. - 3:50 p.m.
April 15, 2008 4/15/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m.  
April 16, 2008 4/16/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m.
April 17, 2008 4/17/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m. Disruptive testing: 6:00 p.m. - 6:50 p.m.
XRF takeover: 7:15 p.m. - 8:15 p.m.
April 18, 2008 4/18/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m.  
April 19, 2008 4/18/2008 continuation of testing from Friday 10:00 a.m. - 2:00 p.m.   
April 20, 2008 N/A N/A N/A Testing not available
April 21, 2008 4/21/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m. XRF takeover: 8:30 a.m. - 9:30 a.m.
Disruptive testing: 3:00 p.m. - 3:50 p.m.
April 22, 2008 4/22/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m.  
April 23, 2008 4/23/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m.  
April 24, 2008 4/24/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m. Disruptive testing: 6:00 p.m. - 6:50 p.m.
XRF takeover: 7:15 p.m. - 8:15 p.m.
April 25, 2008 4/25/2008 prior day test activity applied 7:30 a.m. - 4:00 p.m. Early Close
April 26, 2008 N/A N/A N/A DIT Closed
April 27, 2008 N/A N/A N/A Testing not available
April 28, 2008 4/28/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m. XRF takeover: 8:30 a.m. - 9:30 a.m.
Disruptive testing: 3:00 p.m. - 3:50 p.m.
April 29, 2008 4/29/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m.  
April 30, 2008 4/30/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m.  

May 2008

Date Cycle Date Holdings Database Hours Testing Notes
May 1, 2008 N/A N/A N/A Closed - Refresh Databases
May 2, 2008 5/2/2008 4/30/2008
No P&I activity processed.
7:30 a.m. - 11:30 p.m.  
May 3, 2008 N/A N/A N/A DIT closed. No customer testing.
May 4, 2008 N/A N/A N/A Testing not available
May 5, 2008 5/5/2008 Prior day test activity applied.P&I payment wires processed through the end of the month. P&I notifications available upon request. 7:30 a.m. - 11:30 p.m. XRF takeover: 8:30 a.m.-9:30 a.m.
Disruptive testing: 3:00 p.m. - 3:50 p.m.
May 6, 2008 5/6/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m.  
May 7, 2008 5/7/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m.  
May 8, 2008 5/8/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m. Disruptive testing: 6:00 p.m. - 6:50 p.m.
XRF takeover: 7:15 p.m. - 8:15 p.m.
May 9, 2008 5/9/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m.  
May 10, 2008 5/9/2008 continuation of testing from Friday 10:00 a.m. - 4:00 p.m.   
May 11, 2008 N/A N/A N/A Testing not available
May 12, 2008 5/12/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m. XRF takeover: 8:30 a.m. - 9:30 a.m.
Disruptive testing: 3:00 p.m. - 3:50 p.m.
May 13, 2008 5/13/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m.  
May 14, 2008 5/14/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m.  
May 15, 2008 5/15/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m. Disruptive testing: 6:00 p.m. - 6:50 p.m.
XRF takeover: 7:15 p.m. - 8:15 p.m.
May 16, 2008 5/16/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m.  
May 17, 2008 5/16/2008 continuation of testing from Friday 10:00 a.m. - 2:00 p.m.   
May 18, 2008 N/A N/A N/A Testing not available
May 19, 2008 5/19/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m. XRF takeover: 8:30 a.m. - 9:30 a.m.
Disruptive testing: 3:00 p.m. - 3:50 p.m.
May 20, 2008 5/20/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m.  
May 21, 2008 5/21/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m.  
May 22, 2008 5/22/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m. Disruptive testing: 6:00 p.m. - 6:50 p.m.
XRF takeover: 7:15 p.m. - 8:15 p.m.
May 23, 2008 5/23/2008 prior day test activity applied 7:30 a.m. - 4:00 p.m. Early Close
May 24, 2008 N/A N/A N/A Testing not available
May 25, 2008 N/A N/A N/A Testing not available
May 26, 2008 N/A N/A N/A Closed - Holiday
May 27, 2008 5/27/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m.  
May 28, 2008 5/28/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m.  
May 29, 2008 5/29/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m. Disruptive testing: 6:00 p.m. - 6:50 p.m.
XRF takeover: 7:15 p.m. - 8:15 p.m.
May 30, 2008 5/30/2008 prior day test activity applied 7:30 a.m. - 6:30 p.m.  
May 31, 2008 5/30/2008 continuation of testing from Friday 10:00 a.m. - 2:00 p.m.   

June 2008

Date Cycle Date Holdings Database Hours Testing Notes
June 1, 2008 N/A N/A N/A Testing not available
June 2, 2008 N/A N/A N/A Closed - Refresh Databases
June 3, 2008 6/3/2008 05/30/2008
No P&I activity processed.
7:30 a.m. - 11:30 p.m.  
June 4, 2008 6/4/2008 Prior day test activity applied.P&I payment wires processed through the end of the month. P&I notifications available upon request. 7:30 a.m. - 11:30 p.m.  
June 5, 2008 6/5/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m. Disruptive testing: 6:00 p.m. - 6:50 p.m.
XRF takeover: 7:15 p.m. - 8:15 p.m.
June 6, 2008 6/6/2008 prior day test activity applied 7:30 a.m. - 4:00 p.m. Early Close
June 7, 2008 N/A N/A N/A DIT Closed - FRB Contingency Test
June 8, 2008 N/A N/A N/A Testing not available
June 9, 2008 6/9/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m. XRF takeover: 8:30 a.m. - 9:30 a.m.
Disruptive testing: 3:00 p.m. - 3:50 p.m.
June 10, 2008 6/10/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m.  
June 11, 2008 6/11/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m.
June 12, 2008 6/12/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m. Disruptive testing: 6:00 p.m. - 6:50 p.m.
XRF takeover: 7:15 p.m. - 8:15 p.m.
June 13, 2008 6/13/2008 prior day test activity applied 7:30 a.m. - 6:30 p.m.
June 14, 2008 6/13/2008 continuation of testing from Friday 10:00 a.m. - 2:00 p.m.  
June 15, 2008 N/A N/A N/A Testing not available
June 16, 2008 6/16/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m. XRF takeover: 8:30 a.m. - 9:30 a.m.
Disruptive testing: 3:00 p.m. - 3:50 p.m.
June 17, 2008 6/17/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m.  
June 18, 2008 6/18/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m.  
June 19, 2008 6/19/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m. Disruptive testing: 6:00 p.m. - 6:50 p.m.
XRF takeover: 7:15 p.m. - 8:15 p.m.
June 20, 2008 6/20/2008 prior day test activity applied 7:30 a.m. - 6:30 p.m.  
June 21, 2008 6/20/2008 continuation of testing from Friday 10:00 a.m. - 4:00 p.m.   
June 22, 2008 N/A N/A N/A Testing not available
June 23, 2008 6/23/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m. XRF takeover: 8:30 a.m. - 9:30 a.m.
Disruptive testing: 3:00 p.m. - 3:50 p.m.
June 24, 2008 6/24/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m.  
June 25, 2008 6/25/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m.  
June 26, 2008 6/26/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m. Disruptive testing: 6:00 p.m. - 6:50 p.m.
XRF takeover: 7:15 p.m. - 8:15 p.m.
June 27, 2008 6/27/2008 prior day test activity applied 7:30 a.m. - 6:30 p.m.  
June 28, 2008 6/27/2008 continuation of testing from Friday 10:00 a.m. - 2:00 p.m.   
June 29, 2008 N/A N/A N/A Testing not available
June 30, 2008 6/30/2008 prior day test activity applied 7:30 a.m. - 11:30 p.m. XRF takeover: 8:30 a.m. - 9:30 a.m.
Disruptive testing: 3:00 p.m. - 3:50 p.m.

Top of Page